Fall/Winter 2025 Project Update: West Cedar Lane Water Main Replacement - BT/BR7058A21
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
To enhance service reliability and provide a constant supply of safe, clean drinking water by installing a new 24-inch transmission water main along West Cedar Lane.
Winter 2023 – Winter 2027
Construction is 61% complete.
Water main installation on the first three phases of the project is complete (West Cedar Lane and Rockville Pike).
The contractor is finishing up Phase 4 (West Cedar) and will be pausing construction and removing equipment during the winter months due to restrictions on above-ground pipe (bypass) installation. Work will resume in March 2026.
Construction for the last phases 5 & 6 (Old Georgetown/West Cedar intersection and Oakmont Road) will begin in spring 2026 and will be conducted simultaneously.