Fall/Winter 2025 Project Update: Edward Drive Water Main Replacement - BR6473A18
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
To enhance service reliability and to provide safe, clean drinking water, WSSC Water is replacing our aging infrastructure. This project will replace 1.5 miles of water main ranging from 4 to 10 inches in diameter.
Winter 2025 – Spring 2027
Construction is 5% complete.
Pipe installation has started on Edward Drive and will continue through December.
Please expect no parking signs to be placed where work will occur between the hours of 7:00 a.m. – 5:00 p.m. Work may occasionally extend beyond these hours to complete specific tasks.
Final roadway paving/striping is estimated to be completed in early spring 2027, weather permitting.
Construction will pause from December 24, 2025, to January 1, 2026, except for emergency work if needed. Crews will return after the break to continue planned activities.