alert
Residential Water Service Disconnections begin July 7, 2026
1781296197
close
alert
The Water Fund will begin accepting applications on July 1, 2026.
1781279834
close
alert
Regional Drought Watch
1780510546
close
[Image]
Group of three WSSC Water employees, wearing appropriate safety gear including hardhats and reflective vests, study a document one of them holds. A WSSC Water truck and orange traffic cones are in the background.

Project Purpose

To enhance service and reliability of the water system, WSSC Water is replacing our aging infrastructure including 4-inch, 8-inch, 10-inch and 16-inch diameter water mains.

Project Schedule

Fall 2025 - Fall 2027

Project Status

Construction started on October 31, 2025. 

Construction is approximately 31% complete with a total of 2,078 feet of 16-inch water main installed.

Upcoming work includes continued installation of 16-inch water main. In early 2026, crews will also begin installation of a flow control vault in the vicinity of 9200 Allentown Road.

Key Contacts

WSSC Water Contract Supervisor 

Steven Gray
240-304-1155 
[email protected]

WSSC Water Onsite Inspector 

Dalmung Kuntong  
240-764-9808 
[email protected]

[Image]
Allentown Road Water Main Replacements, Prince George's County. The line segments on Allentown Rd. indicate Phase 1 (from Steed Rd. to unnamed road); Phase 2 (from unnamed toad to close to Stonesboro Rd.); Phase 3 (from Stonesboro Rd. to past Alderton Ave.); Phase 4 (from past Alderton Ave. to Marston Dr.); Phase 5 (from Marston Dr. to past Lucille Dr.); Phase 6 (from Lucille Dr. to Tucker Rd); and Phase 7 (the dark green shape near the intersection of Allentown Rd. and Steed Rd.)

 

Last Modified: February 10, 2026, 10:05 am EST