Fall/Winter 2025 Project Update: Parkwood Drive I Water Main Replacement - BR7270A22
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
To enhance service reliability of the water system, WSSC Water is replacing our aging infrastructure. This project is replacing approximately 4.5 miles of 8-inch and 10-inch diameter water main, to include water house service to the property line.
April 2025 – Spring 2029
Construction is 15% complete.
The contractor has completed all water main replacement work on Woodfield Road and approximately 525 feet of 8-inch water main along Franklin Street between Saul Road and Edgefield Road including installation of new water house connections.
During the winter months, the contractor will continue work on Saul Road, beginning at the intersection of Parkwood Drive, progressing toward Wildwood Road.
Construction will pause from December 24–28, 2025, and again from December 31, 2025–January 4, 2026, except for emergency work if needed. Crews will return after the holiday breaks to continue planned activities.