Project Purpose

To enhance service reliability and to provide safe, clean drinking water, WSSC Water is replacing our aging infrastructure. This project will replace 1.86 miles of water main ranging from 4 to 12 inches in diameter.

Project Schedule

Fall 2025 – Spring 2027

Project Status

Construction is 30% complete.​

Work is currently underway on Dee Lane, Parkview Lane, Upton Lane, and Thrift Road.​

Expect weekday working hours from 9 a.m. to 3:30 p.m.

Work may occasionally extend beyond these hours to complete specific tasks.

Key Contacts

WSSC Water Contract Supervisor 

Tim Allen
301-206-7316 
[email protected]

WSSC Water Onsite Inspector 

Steven Mogel 
240-302-6324 
[email protected]

[Image]
Darlene Drive Water Main Replacement Project, Prince George's County, Maryland. Project Number BR6558A18. The lines (medium blue) shows the water main replacement areas on Upton, Parkview, Darlene, Dee, Wigan, and Terence.

 

Last Modified: May 29, 2026, 11:07 am EDT