Project Purpose

To enhance service reliability and provide safe, clean drinking water, WSSC Water is replacing our aging infrastructure. This project will replace approximately 2.30 miles of water main with new 4-inch to 10-inch diameter water main.

Project Schedule

Winter 2025 – Spring 2026

Project Status

Construction is 90% complete. Pipe installation is complete.​

Installation of the water main on Daniel Drive, Berry Lane, Berry Place, Altamont Place, Bethany Drive, Anny Drive, Brewton Street, Brewton Court, Wintergreen Court, Glendora Drive, and Glendora Court has been completed.​

The contractor demobilized equipment and materials during the winter season and will return in the spring to complete pavement and green space restoration.​

Final roadway paving and striping is estimated to be completed in spring 2026.

Key Contacts

WSSC Water Contract Supervisor 

Earnest Pigatt 
202-603-2456
[email protected]

WSSC Water Onsite Inspector 

Curtis Binion Jr.
240-716-9638  
[email protected]

[Image]
Horizon Way Water Main Replacement. Phase 1 includes Berry Ln., Fowlers Ct., Starshine Dr., Berry Pl., Anny Dr., Bethany Dr., Altamont Pl., & Altamont Ave. Phase 2 is Daniel Dr. Phase 3 includes Brewton St., Brewton Ct., & Winter Green Ct. Phase 4 is Glendora Dr. and Glendora Ct.

 

Last Modified: May 29, 2026, 8:27 am EDT