Spring 2026 Project Update: West Cedar Lane Water Main Replacement - BT/BR7058A21
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
To enhance service reliability and provide safe, clean drinking water, WSSC Water is replacing our aging infrastructure. This project will install new 24-inch transmission main along West Cedar Lane.
Winter 2023 – Winter 2027
Construction is 67% complete. Phases 1, 2, and 3 water main installation are complete. Following a pause during the winter months, the contractor has now resumed work for the spring season.
Phases 5 and 6 will be constructed simultaneously, including work at the Old Georgetown Road and West Cedar Lane intersection and along Oakmont Avenue.
Please expect work to continue in these areas throughout spring 2026.
Mike Krempel
240-848-2418
[email protected]
Oscar Diaz-Sanchez
240-524-8961
[email protected]