Project Purpose

To enhance the service reliability of the sewer system, WSSC Water is replacing our aging infrastructure. This project will rehabilitate 6-inch and 10-inch diameter sewer main and install eleven new sewer manholes.

Project Schedule

Winter 2025 – Spring 2027

Project Status

Construction is 50% complete.​

The contractor is performing sewer mainline and lateral replacement on Crossbow Road.

Final roadway paving and striping is estimated to be completed in early spring 2027.

Key Contacts

WSSC Water Contract Supervisor 

Ron Blount
240-429-4692  
[email protected]

WSSC Water Onsite Inspector

Tracy Mitchell
301-404-8806
[email protected]

[Image]
Suitland Road Sewer Main Rehabilitation Project, Prince George's County, Maryland. Project Number CRCILRMH7309A22. The thick lines (light green) show the sewer main rehabilitation areas.

 

Last Modified: May 29, 2026, 11:46 am EDT