Spring 2026 Project Update: Edward Drive Water Main Replacement - BR6473A18
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
To enhance service reliability and provide safe, clean drinking water, WSSC Water is replacing our aging infrastructure. This project will replace 4-inch, 8-inch, and 10-inch diameter water main.
Winter 2025 – Spring 2027
Construction is 60% complete.
Pipe installation is currently underway on Kaine Drive and Marlee Avenue.
No parking signs will be posted in work areas during construction.
Please expect weekday working hours from 7 a.m. to 5 p.m. Work may occasionally extend beyond these hours to complete specific tasks.
Final roadway paving and striping is estimated to be completed in early spring 2027.