Spring 2026 Project Update: Parkwood Drive I Water Main Replacement - BR7270A22
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
Access the update information WSSC Water provides to customers who live near ongoing water main replacement projects.
To enhance service reliability of the water system, WSSC Water is replacing our aging infrastructure. This project will replace 4.5 miles of 8-inch and 10-inch diameter water main and install new water service connections to the property line.
April 2025 – Spring 2029
Construction is underway. Phase II is currently under construction. Phase II includes installation of approximately 4,750 linear feet of water main along:
This phase also includes installation of new water service connections.
Phase II is anticipated to be completed in spring 2029
Jose A. Viera
240-508-3886
[email protected]
Arun Patel
240-508-3374
[email protected]