alert
Reported Water Main Breaks and Leaks
1769530200
close
alert
Drinking water not impacted by sanitary sewer overflow after collapse of DC Water’s sewer main in Montgomery County.
1769184998
close
[Image]
Group of three WSSC Water employees, wearing appropriate safety gear including hardhats and reflective vests, study a document one of them holds. A WSSC Water truck and orange traffic cones are in the background.

Project Purpose

The purpose of this project is to strategically replace and rehabilitate aging infrastructure to enhance service and reliability to customers. This project is installing 0.36 miles of sewer force main, 0.15 miles of sewer mains and sewer force mains.

Project Schedule

Fall 2025 – Fall 2026

Project Status

WSSC Water’s contractor, Ross, began mobilizing on October 14, 2025. Construction of the access road along Huron Drive began on October 15, 2025. Ross is currently working on a 60-inch manhole at the intersection of Indian Head Highway and Audrey Lane.

Winter Holiday Schedule

Construction will pause from December 24, 2025, to January 1, 2026, except for emergency work if needed. Crews will return after the break to continue planned activities.

Key Contacts

WSSC Water Contract Supervisor 

Justin Clark 
240-761-7311  
justin.clark@wsscwater.com

WSSC Water Onsite Inspector 

Zack Sydnor  
301-213-5806  
zack.sydnor@wsscwater.com

[Image]
Forest Heights Force Main Replacement Project, Prince George's County. The thick lines on the map (light blue) show the main replacement location, which runs along Audrey Lane from Indian Head Highway to N. Huron Drive.

 

Last Modified: February 6, 2026, 8:40 am EST