Project Purpose

The purpose of this project is to strategically replace and rehabilitate aging infrastructure to enhance service and reliability to customers. This project is installing 0.36 miles of sewer force main, 0.15 miles of sewer mains and sewer force mains.

Project Schedule

Fall 2025 – Fall 2026

Project Status

WSSC Water’s contractor, Ross, began mobilizing on October 14, 2025. Construction of the access road along Huron Drive began on October 15, 2025. Ross is currently working on a 60-inch manhole at the intersection of Indian Head Highway and Audrey Lane.

Winter Holiday Schedule

Construction will pause from December 24, 2025, to January 1, 2026, except for emergency work if needed. Crews will return after the break to continue planned activities.

Key Contacts

WSSC Water Contract Supervisor 

Justin Clark 
240-761-7311  
[email protected]

WSSC Water Onsite Inspector 

Zack Sydnor  
301-213-5806  
[email protected]

[Image]
Forest Heights Force Main Replacement Project, Prince George's County. The thick lines on the map (light blue) show the main replacement location, which runs along Audrey Lane from Indian Head Highway to N. Huron Drive.

 