Fall/Winter 2025 Project Update: Beaverdam Basin Sewer Rehabilitation - CI6311B17
Access the update information WSSC Water provides to customers who live near ongoing sewer rehabilitation projects.
Access the update information WSSC Water provides to customers who live near ongoing sewer rehabilitation projects.
To enhance service and reliability of the sewer system, WSSC Water is renewing our aging infrastructure. This project will rehabilitate 6-inch and 10-inch diameter sewer mains. Three new sewer manholes will also be installed.
Summer 2023 – Summer 2026
Construction is 90% complete. Pipe work is estimated for completion in April 2026.
Remaining construction is located at 5000 Tuxedo Road and 6202-6225 L Street.
Please expect weekday lane closures from 8:00 a.m. – 4:00 p.m. Work may occasionally extend beyond these hours to complete specific tasks. Final roadway paving/striping is estimated to be completed in summer 2026.
Construction will pause from December 24, 2025, to January 1, 2026, except for emergency work if needed. Crews will return after the break to continue planned activities.