A. Identification and Coding Information
| Agency Number | Project Number | Update Code | PDF Date | Date Revised | Pressure Zones | Drainage Basins | Planning Areas |
|---|---|---|---|---|---|---|---|
| W - 000073.33 | 173801 | Change | October 1, 2025 | - | Potomac WFP HGPOWF | - | Bi-County |
B. Expenditure Schedule (000s)
| Cost Elements | Total | Thru FY25 | Estimate FY26 | Total 6 Years | Year 1 FY27 | Year 2 FY28 | Year 3 FY29 | Year 4 FY30 | Year 5 FY31 | Year 6 FY32 | Beyond 6 Years |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Planning, Design and Supervision | 24,875 | 22,009 | 1,623 | 1,243 | 1,243 | - | - | - | - | - | - |
| Land | 1,000 | 1,000 | - | - | - | - | - | - | - | - | - |
| Construction | 197,755 | 164,255 | 22,500 | 11,000 | 11,000 | - | - | - | - | - | - |
| Other | 1,818 | - | 1,206 | 612 | 612 | - | - | - | - | - | - |
| Total | 225,448 | 187,264 | 25,329 | 12,855 | 12,855 | - | - | - | - | - | - |
C. Funding Schedule (000s)
| Cost Elements | Total | Thru FY25 | Estimate FY26 | Total 6 Years | Year 1 FY27 | Year 2 FY28 | Year 3 FY29 | Year 4 FY30 | Year 5 FY31 | Year 6 FY32 | Beyond 6 Years |
|---|---|---|---|---|---|---|---|---|---|---|---|
| WSSC Bonds | 225,448 | 187,264 | 25,329 | 12,855 | 12,855 | - | - | - | - | - | - |
D. Description and Justification
Description
The Potomac WFP Consent Decree Program provides for the planning, design, and construction required for the implementation of Short-Term Operational and Long-Term Capital Improvements at the Potomac Water Filtration Plant (WFP) to allow WSSC Water to meet the new discharge limitations identified in the Consent Decree.
Justification
The Consent Decree (CD) was Entered by the U.S. District Court of Maryland on April 15, 2016. Under the terms of the CD WSSC Water is required to “undertake short-term operational changes and capital improvements at the Potomac WFP that will enable WSSC Water to reduce significantly the pounds per day of solids discharged to the River” (CD Section II. Paragraph 6.i); and to plan, design, and implement long-term “upgrades to the existing Plant or to design and construct a new plant to achieve the effluent limits, conditions, and waste load allocations established by the Maryland Department of the Environment (the Department) and/or in this Consent Decree, and incorporated in a new discharge permit to be issued by the Department” (CD Section II. Paragraph 6.ii).
The CD required WSSC Water to submit a Draft Audit Report and Draft Long-Term Upgrade Plan to the Citizens and the Department by November 15, 2016, and final reports to the Citizens and the Department by January 1, 2017. The Final Audit and Long-Term Upgrade Plan Reports were submitted to the Citizens and the Department on December 29, 2016. The Department reviews the Audit Report and selects recommended improvements in operations, monitoring, and waste tracking, along with select capital projects that can be completed no later than April 1, 2020 and that are necessary to achieve the goals identified in CD Section IV. Paragraph 24. Additionally, the work required to implement the Long-Term Capital Improvements Project(s) shall be fully implemented in accordance with the schedule set forth in the Long-Term Upgrade Plan. In March of 2025, the parties agreed to amend the January 1, 2026, substantial completion deadline to October 11, 2026.
Cost Change
The schedule and expenditure projections were revised based upon the amount of time and funding required to complete the remaining projects in this program.
Other
The schedule and expenditure projections shown in Block B above are based on actual bids and include $1,000,000 for Supplemental Environmental Projects included under CD Section IX. Paragraph 50. WSSC Water Green Bonds will be utilized to fund a portion of this project. The reduction in suspended solids discharged into the Potomac River will address the following International Capital Market Association (ICMA) Green Bond Principles 2016 categories: Pollution prevention/control; and Terrestrial and aquatic biodiversity conservation.
Coordination
Coordinating Agencies:
- Maryland Department of the Environment
- Montgomery County Government
- National Park Service
- Prince George’s County Government
- U.S. Environmental Protection Agency, Region III
Coordinating Projects:
- W - 000073.30 - Potomac WFP Submerged Channel Intake
- W - 000073.32 - Potomac WFP Main Zone Pipeline
E. Annual Operating Budget Impact (000s)
| Impact Category | Amount of Impact | FY of Impact |
|---|---|---|
| Staff and Other | - | - |
| Maintenance | - | - |
| Debt Service | $13,841 | 28 |
| Maintenance | - | - |
| Total Cost | $13,841 | 28 |
| Impact on Water and Sewer Rate | $0.03 | 28 |
F. Approval and Expenditure Data (000s)
- Date first in program: FY17
- Date first approved: FY16
- Initial cost estimate: 27,250
- Cost estimate last FY: 218,954
- Present cost estimate: 225,448
- Approved request last FY: 38,717
- Total expense and encumbrances: 187,264
- Approval request Year 1: 12,855
G. Status Information
- Land status: Land acquired
- Project phase: Construction
- Percent complete: 78%
- Estimated completion date: June 2027
- Growth: N/A
- System improvement: N/A
- Environmental regulation: 100%
- Population served: N/A
- Capacity: N/A
H. Map