WSSC Water installed 2.5 miles of new 48-inch raw water pipeline from the Rocky Gorge Raw Water Pumping Station to the Patuxent Water Filtration Plan, location along MD 198.

The new pipeline increases the Patuxent Water Filtration Plant’s production to meet the drinking water needs of Prince George’s and Montgomery County residents while ensuring infrastructure resiliency and redundancy.

Project Audit

In July 2025, WSSC Water engaged WSP USA, Inc., an outside consulting firm, to conduct an independent evaluation and audit of this pipeline project. The goal of this independent review was to identify the underlying root causes of the challenges encountered and capture lessons learned to strengthen future project delivery.

Project Audit Reports

[Image]
QR code for Patuxent Project Comment Form

Project Comment Form

The Project Comment Form provides an opportunity to share questions or feedback about the audit report. Submissions will be reviewed and addressed after the public comment period concludes. 48-inch Patuxent Raw Water Project (Bond Mill Rd) Project Comment Form 

Public Comment Submission Timeline
November 19, 2025, through December 19, 2025.

Disclaimer
By clicking the link, you will be leaving WSSC Water’s website and redirected to WSP’s external site to submit comments and/or questions.