Background – Greenbelt Standpipe Rehabilitation
The Greenbelt Standpipe is a two-million-gallon steel elevated water storage facility located at 211 Ridge Rd, Greenbelt Maryland. The elevated tank and associated inlet/outlet piping on site were constructed in 1936 and nearing the end of their service life.
WSSC Water purchased the adjacent property at 241 Lastner Lane, which currently includes an existing dwelling. As part of the project scope, this dwelling will be demolished. Incorporating the additional area into the site will help reduce construction costs, provide a safer working environment for crews, and enhance WSSC Water’s ability to maintain the facility in the future.
Project Scope
Site Work
The project calls for replacing existing facility yard piping and valve vaults, which will connect to the existing water main located at Ridge Road and Lastner Lane. Site work will also include a new perimeter security fence/gate and repaving of the site driveway. The site will have new landscaping which includes trees, bushes, and a pollinator garden.
Structural
Due to the age of the facility, upgrades to the structural steel and concrete foundation are included as part of the project which will extend the service life of the tank. This portion of the project also includes updating ladders, balconies and tank access to meet current Occupational Safety and Health Administration (OSHA) standards to ensure WSSC Water personnel can maintain and work around and, on/in the tank safely.
Tank Coating
The tank's interior and exterior will be recoated with a new epoxy-based coating that will protect the tank from corrosion and have a service life of 25 years. The process includes removing the existing coating by abrasive blasting, then cleaning and preparing the surface before the new coating is applied.
Containment System
A Class 2-A containment system will be erected around the existing tank structure to provide two important functions:
- To contain particles from the removal of the existing coating within the system. The contractor will abide by OSHA, Environmental Protection Agency (EPA), and all other applicable codes for disposing of the waste produced from the coating removal process.
- To prevent overspray during the painting process.
Water Quality
Throughout rehabilitation, the tank will be drained and out of service, isolated from the water system. After the construction completion, the tank will be cleaned and disinfected by WSSC Water. We will also collect water samples for testing; results must be approved by the Maryland Department of the Environment (MDE) before returning the tank to service.
Community Impact
The majority of the community will have no water service impact during the rehabilitation process.
However, during the project there will be an approximately four hour water service shutdown related to the service tie-in that will affect approximately eleven (11) homes on Lastner Lane. Affected residents will receive advance notification with more information prior to the scheduled shutdown.
Residents in the area should expect minor traffic impacts due to the delivery of materials and equipment to the project site. To help minimize disruptions, no deliveries to the site will occur between 8:15 a.m.–10:00 a.m. and 2:30 p.m.–4:00 p.m. to avoid school bus pick-up or drop-off.
Construction Schedule and Timing
The contractor is expected to mobilize to the project site in early November to install sediment control and soil erosion measures.
Additional Information
- Notification of Project Letter - August 14, 2025
- Notification of Construction Start Letter - October 24, 2025
- Public Outreach Community Meeting Presentation - November 12, 2025
Location Map
Contact
Christopher DeHerde - WSSC Water Project Manager – (301) 206-8560
(Please email any questions to Christopher.Deherde@wsscwater.com)