Project Purpose & Status
WSSC Water installed 2.5 miles of new 48-inch raw water pipeline from the Rocky Gorge Raw Water Pumping Station to the Patuxent Water Filtration Plant, location along MD 198. The project was completed in August 2025. Project milestones include:
- Pipe installation - December 2024
- Roadway paving - May 2025
- Restoration and tree planting - June 2025
- Roadway striping and installation of raised crosswalks - August 2025
The new pipeline increases the Patuxent Water Filtration Plant’s production to meet the drinking water needs of Prince George’s and Montgomery County residents while ensuring infrastructure resiliency and redundancy.
To view past presentations and updates on this project, please scroll down to the bottom of the page.
Project Audit
In July 2025, WSSC Water engaged WSP USA, Inc., an outside consulting firm, to conduct an independent evaluation and audit of this pipeline project. The goal of this independent review was to identify the underlying root causes of the challenges encountered and capture lessons learned to strengthen future project delivery.
Project Audit Reports
- Patuxent Project Audit Report
- Patuxent Project Audit Report - Appendix
- Patuxent Project Audit Report - Executive Summary Memo