Submerged Potomac River Intake Feasibility Study Schedule
- Study start - August 2003
- Initiation report - February 2004
- Public informational workshop -March 2004
- Existing conditions & data report - June 2004
- Permit requirements - Spring 2004
- Development of alternatives -Late spring 2004
- Review of preliminary alternatives -Fall 2004
- Alternative development & evaluation criteria report - July 2005
- National Environmental Policy Act (NEPA) assessment application - Fall 2005 <<-- WE ARE HERE on Fall 2005
- NEPA public review -Winter 2005/2006
- Public informational workshop -Winter 2005/2006
- Final feasibility study - Spring 2006
- County council review - Spring 2006
|