Submerged Potomac River Intake Feasibility Study Schedule

  • Study start - August 2003
  • Initiation report - February 2004
  • Public informational workshop -March 2004
  • Existing conditions & data report - June 2004
  • Permit requirements - Spring 2004
  • Development of alternatives -Late spring 2004
  • Review of preliminary alternatives -Fall 2004
  • Alternative development & evaluation criteria report - July 2005
  • National Environmental Policy Act (NEPA) assessment application - Fall 2005   <<-- WE ARE HERE on Fall 2005
  • NEPA public review -Winter 2005/2006
  • Public informational workshop -Winter 2005/2006
  • Final feasibility study - Spring 2006
  • County council review - Spring 2006

 