Preliminary subdivision plans that are submitted to either the Montgomery or Prince George's MNCP&PC for approval will be reviewed by the WSSC to determine the availability of water and sewer service, make recommendations, and note special conditions. A representative from WSSC will attend the development review committee meetings in Montgomery County and the subdivision review committee meetings in Prince George's County to discuss WSSC's findings with the Applicant and the committee. General review comments will be provided at the MNCP&PC meeting. It should be understood that new and additional review comments are likely when more detailed information on the proposed public extension(s) is provided during the hydraulic planning analysis and system integrity review processes for SEP projects and during the feasibility review and design stage for Non-SEP projects.
|
|
*** THIS STAGE TAKES APPROXIMATELY 2 WEEKS ***
|
 |